Improvement and Development of Imam Khomeini Airport Passenger Terminal

Client Imam Khomeini International Airport Office
Location Tehran, Iran
Scope Of Work Engineering, Procurement and Construction (EPC)

Project Detail

Contract Type
Engineering,
Procurement & Construction
Location
Tehran, Iran
Executive stage
Final Handover
Physical Progress
100%
Commencement Date
Jul., 5, 2009
Initial Duration
24 months 
Brief Description
Development of Imam Khomeini International Airport is proposed to double the capacity of passengers’ transportation with an EPC contract. In addition, the costume service, administration and cargo area has been increased by 70 % of its initial situation.
Technical Specification
The development works with thearea of 22,000 square meters including: Adding two pier structures at the right and left side of the existing plan.
Development of administration and costume building at the right and left side of the existing plan.
Adding recreational and food court area to the down side of the existing plan. Disassembly and Re-assembly of the complex existing facade due
to the development works.
General works’ Quantity
Earth works 20,000 m³
Concreting 9,000 m³
Reinforcement 1,200 tons
Formworking 30,000 m²
Metal works 1,000 tons